Construction Management Claims: What to know?

United Seattle • December 7, 2022

Construction Claim Procedure According To FIDIC Redbook

A wooden gavel sits on top of a book of law

Construction is quite a complex project, and to complete it successfully, proper construction management is needed. Management of all the resources, like labor, material equipment, contractors, engineers, etc., is inevitable. Only then a construction project can be successful.

But sometimes the management is so insufficient that numerous issues arise, which are the main reasons for the construction claims like the bond claims, mechanic lien claims, delay claims, etc. In this article, you will learn about construction claims and the reasons for them.


What Is a Construction Claim?

A claim is a dispute caused by one party requesting something from the opposite party. Various reasons can serve as the precursor to the claims, and almost every project faces a claim.

Construction claims are quite different from the change order. In the change order, both parties are in agreement, whereas in the claim, one party does not agree with the other, which results in further negotiation, mediation, arbitration, and litigation.

Construction claims can be turned into the change order if both parties negotiate effectively and agree; otherwise, proper resolution of the claim is needed.


What Are The Causes Of The Construction Project Management Claims?

Although there are various causes of construction claims, it is usually recommended to treat the root cause, which is to avoid these from the early stages. It was reported that most of the time, construction claims mainly occur during the project's construction phase. That is why it is recommended that construction management should be done effectively from the start.

The following can be some causes of the construction claims:

•     Site handover delay

•     Delay in drawing supply

•     Any design error occurred

•     Any severe weather condition

•     Injuries to the labor due to accidents

•     Frequent changes in plans or designs

•     Loss of equipment or faults in equipment

•     Delays in the payments can lead to construction lien

•     Due to some other legal issues etc.


Construction Claim Procedure According To FIDIC Redbook

FIDIC contracts hold importance when it comes to construction contracts as they are consulted all over the world regarding agreements. They have various contracts that were created keeping in mind the multiple types of construction and installation projects, so there are standard principles to follow whenever any agreement occurs.


One of the essential contracts is the FIDIC Redbook 1999 edition, based on the "Condition of Contract for Construction for Building and Engineering Works."

According to this contract, the construction work Is solely based on the design made by the employer. Generally, in the projects, the work is done according to the contractors, but here the work is based on the design provided by the employer. Moreover, the payment is made every month based on the sum of items of work.


Steps Of Construction Project Management Claims

The following steps take place in Construction claims management:

•     Prevention Of The Claim

Prevention of the claims is the first step, and this starts from the initial phase of the project. All the necessary information is documented, like the initial contracts, plans, or design, so the claims can be prevented.

•     Pursuing Of The Claim

In this step, first of all, the claim is identified in which the claim is analyzed with the help of contract documents and its scope. After complete analysis, the claim quantification happens in which cost and the time impact are calculated, and a cost is estimated.

•     Resolution Of The Claim

After all the steps and analysis of the claims comes the resolution part. Although it is best to negotiate the claim if that does not happen, further steps like mediation, arbitration, and litigation take place.


Running Construction Projects Smoothly

Construction claims like delays or mechanic liens are part of the projects, and construction projects can often face these. Managing these effectively and treating the root cause essential for the construction project to run smoothly.

By Victor K • September 22, 2026
General contractors or GC often look out for a complete package in their commercial subcontractor Seattle. The enormous task of combining multiple commercial construction subcontractor Seattle for a single project is a recipe for disaster and all GCs know this well. However, when it comes to selecting that one, the cost bid must not be the only criterion. The lowest bid might not have the overall expertise that is required for the project. GCs can bundle all the tasks and award them to one construction management subcontractor. However, the cost comparison between a single commercial subcontractor Seattle or multiple ones is not linear as lower coordination costs, fewer scope gaps, and better schedule control must also be taken into account. Total Installed Cost Vs. Trade Pricing In simple mathematical terms, the total project cost is just the amount the commercial subcontractor Seattle charges the GC. However, factors like Trade bid price, coordination cost, schedule exposure and change-order exposure must also be taken into account while pricing for a singular or multiple construction management subcontractors. The GC can simply request a quote for each task, generate competition and get the lower cost. However, the factors listed account for additional cost in this scenario as the GC needs to coordinate multiple contracts, schedules, site mobilizations, foremen, RFIs, submittals, invoices, inspections, and handoffs. A single-source commercial subcontractor Seattle like United Seattle may cost more than a competitive breakdown of subtasks but the additional factors are eliminated and long-term cost and time savings are achieved. Schedule Float Vs. Small Bid Difference Multiple tasks have multiple timelines which are often linear rather than parallel. This means that one commercial construction subcontractor Seattle needs to wait for the other one to complete their task before starting. An ideal example of this is flooring and drywall installation. One cannot be done before the first task is completed. A delay in the earlier task can lead to delays, extra cost and rising disputes, all of which have a price tag that the GC has to pay. Therefore, calculations are to be carried out before using multiple contractors rather than one. For example, if a bundled subcontractor costs $30,000 more than the combined lowest trade bids but gives the project team additional schedule flexibility and reduces the likelihood of a costly sequencing delay, that $30,000 should not be evaluated in isolation.
By Victor K • September 14, 2026
Learn how to vet a commercial subcontractor before signing. Check licensing, bonding, insurance, safety, capacity, references, and project management.
By Victor K • August 25, 2026
Managing a construction project is not just about outsourcing all the tasks; it involves much more than meets the eye. It is about being on the project from start to end and checking that all timelines are being followed by every commercial subcontractor Seattle. Scheduling and adhering to timelines are among the most challenging tasks, as it can result in loss of time and resources. The ideal method for a general contractor is to select a commercial construction subcontractor Seattle that provides all the required services. The result can be a more coordinated workflow, clearer accountability, and fewer opportunities for one trade to disrupt another.= The Challenge of Managing Multiple Trade Subcontractors Generally, a major construction job consists of multiple facets, resulting in the hiring of multiple commercial subcontractors in Seattle. These tasks include siding , roofing, flooring , interior design and paint jobs . Different construction management subcontractors bring different flavors to the table and managing them takes special skills on the part of the general contractor. These various companies also bring their own timelines which can result in slowing down the project as most of these tasks need to be completed in a series manner rather than in parallel. The main challenge is not the number of commercial subcontractor Seattle involved in the project but handling their cohesiveness. Every additional handoff creates another opportunity for something to fall through the cracks.
More Posts

We Offer All the Services You Need in One Place! We Will Save You Time and Money!

Call Us at (425) 332-8088 Now to Get a Free Estimate or a Free Consultation for Any of Our Services!

Contact Us